Customer :
EXXONMOBIL
Role :
HORIZONTAL DIRECTIONAL DRILLING
Key date :
2011-2013
Location :
PAPUA NEW GUINEA - Australia
Description of the Project
PNG LNG Project
Horizontal Directional Drilling works
- One 8” HDD Ridge crossing to install the CPF Condensate Pipeline – 792 m+ 6” FOCA Casing in fractured limestone
- Four 32” HDD crossings to install the LNG Project Gas Pipeline in alluvium
Work done and added value of our solution
- Kikori River crossing: 900 m x 16” Gas Pipe + 900 m 6” FOCA Casing.
- Wah River crossing: 556 m x 16” Gas Pipe +556 m x 6” FOCA Casing.
- Mubi River crossing: 673 m x 16” Gas Pipe + 673 m x 6” FOCA Casing.
- Tagari River crossing: 811 m x 16” Gas Pipe + 811 m x 8” Condensate Pipe + 811 m x 6” FOCA Casing.
There has been no pollution of the rivers, thanks to the Horizontal Directional Drilling technique.